Blog Title

Published June 2021, Updated April 2023

How to Balance CLINs in a MILCON Schedule

Published January 2023

NAVFAC Scheduling Specification and Standards : Top 5 Takeaways with Examples

In this article, we’re going to talk about NAVFAC’s scheduling specification and the top 5 takeaways with snapshots and examples.


Similar to other federal agencies, NAVFAC requires the project schedule to manage the project (for both contractor and government activities), evaluate time extensions, and serve as the basis for progress payments.


Contractor schedules can be rejected by the government when they don’t comply with the scheduling requirements, potentially leading to project issues or delays with progress payments.


This article pulls out the top 5 things to know from NAVFAC’s standard 01 32 17.00 20 scheduling specification, which can be found at the UFGS website here.


(As with all our articles, this is for information only. Since individual project requirements may differ, refer to your contract to confirm the requirements).


Top 5 takeaways:


  •   NAVFAC “Network Analysis Schedule” = “NAS” = The Schedule
  •   Cost Loaded Schedule as the Basis for Progress Payments
  •   Interface with 3-Phase Quality Control
  •   NAVFAC Look-Ahead Schedule Requirements
  •   Schedule Milestone and Constraints

      Source: UFGS 01 32 17.00 20, updated May-2018

      After the network diagram has been built per PDM, the critical path method (CPM) is a calculation performed by the scheduling software that runs a forwards and backwards pass through the schedule. This provides each activity’s early/late dates, float values, and ultimately the critical path.
      NAVFAC Schedule PDM and CPM

      The schedule’s network analysis type needs to be the Precedence Diagram Method (PDM). This is a method of scheduling that logically ties all schedule activities together to form a network diagram – the most common form of scheduling today.


      NAVFAC Scheduling Specifications and Standards

      Source: UFGS 01 32 17.00 20, updated May-2018

      The NAVFAC scheduling specifications refer to the project schedule as the “Network Analysis Schedule”, or the “NAS”.

      Whenever you hear the government referring to “the NAS”, it simply means “the schedule”.

      NAVFAC “Network Analysis Schedule” = “NAS” = The Schedule

      To lean more about what a S-Curve from a construction schedule (with examples), see our article here.


      Contractor Cost Loading Tips from 01 32 17.00 20:


      • Don’t include costs for mobilization, except for batch plant set-up, mobilization of dredging equipment, or other similar labor-intensive activities.


      • Review your specs to see if it requires a certain percentage of contract costs for commissioning, testing, and closeout activities.


      • Don’t assign costs to any activities that are government responsibility.


      • Evenly distribute overhead and profit costs to work-in-place activities throughout the project.


      • If you plan on requesting payment for particular work, make sure you have it detailed in the schedule with the costs assigned.


      Source: UFGS 01 32 17.00 20, updated May-2018

      NAVFAC SVC Diagram S-Curve

      The Schedule Variance Control (SVC) Diagram or the S-Curve:

      Source: UFGS 01 32 17.00 20, updated May-2018

      NAVFAC Schedule Earned Value Report

      The cost loading is also used to develop the earned value reports, which include:

      The Earned Value Report as part of the Monthly Update:

      NAVFAC Schedule Cost Loading Example

      Instead of having a separate schedule of values and project schedule, they’re combined into a cost-loaded project schedule.

      Source: UFGS 01 32 17.00 20, updated May-2018

      NAVFAC Schedule Cost Loading

      Cost Loaded Schedule as the Basis for Progress Payments

      As we talked about in our Schedule Cost Loading article, the cost loaded schedule becomes the basis for the government to determine contract earnings for progress payments.

      Source: UFGS 01 32 17.00 20, updated May-2018

      Source: UFGS 01 32 17.00 20, updated May-2018

      NAVFAC Schedule Dates Match QC Reports

      Additionally, the schedule’s actual start and finish dates need to match those in the contractor’s Quality Control daily reports.

      NAVFAC Schedule NAS

      In the NAS: Construction activities represent work involved with the Follow-Up Phase. (Since the Follow-Up Phase consists of daily monitoring and inspections, the NAS doesn’t need to include individual 1-day inspection activities as it’s inherent in the construction activities).

      NAVFAC Look Ahead Schedule Example

      In the 3 Week Lookahead Schedule: The Preparatory and Initial Phase meetings need to be shown for each definable DFOW.

      NAVFAC Schedule Construction Quality Management

      Interface with 3-Phase Quality Control

      There are specific scheduling requirements for how the schedule needs to interface with the contractor’s Quality Control system and definable features of work (DFOW).


      The contractor’s Quality Control plan lists out the DFOWs, which groups the work into specific trades, types, or disciplines. Each DFOW requires the 3-Phase Quality Control system: Preparatory Phase, Initial Phase, and Follow-Up Phase.

      NAVFAC Schedule Look Ahead Example

      The snapshot below highlights the columns to show the NAS Activity ID, Look Ahead Activity ID, and Original Duration (5 work days or less).


      NAVFAC NAS Schedule Look Ahead Requirements

      Source: UFGS 01 32 17.00 20, updated May-2018

      NAVFAC Look-Ahead Schedule Requirements

      The specifications describe level of detail requirements for the NAS, which include:

      • work-in-place activities not exceeding 20 working days (1 month), and
      • separate activities for each phase, area, floor level, and location that the work is occurring.


      For a greater level of detail, the Look-Ahead Schedule captures activities no more than 5 work days in duration.


      This is a schedule derived from the NAS but maintained separately.


      The Look-Ahead Schedule needs to list the parent NAS activity number so the government can refer back to the project’s overall schedule.


      NAVFAC NAS Milestone and Constraint Requirements

      Schedule Milestones and Constraints

      There are various milestones and constraint types required, and below is a chart that compiles these requirements.


      In this article, we talked about NAVFAC’s scheduling specification and the top 5 takeaways with snapshots and examples.

      o    NAVFAC “Network Analysis Schedule” = “NAS” = The Schedule. When you see or hear the term “Network Analysis Schedule”, or “NAS”, it simply means “the schedule”.

      o    Cost Loaded Schedule as the Basis for Progress Payments. Instead of having a schedule of values and a project schedule, they’re combined into a single tool: the cost-loaded project schedule.

      o    Interface with 3-Phase Quality Control. The Look Ahead schedule needs to include the Preparatory and Initial Phase meetings for each definable feature of work (DFOW). The NAS includes Follow-Up Phase activities which are inherent in the construction activities.

      o    NAVFAC Look-Ahead Schedule Requirements. The Look Ahead schedule is derived from the NAS but maintained separately, with a greater level of detail and activity durations that cannot be more than 5 work days long.

      o    Schedule Milestone and Constraints. See the chart above which captures required milestone names, types, and constraint types.


      New to NAVFAC projects as a construction contractor and looking to save time and streamline your workflow? Check out our NAVFAC P6 schedule template files here.


      Summary

      Training + Tools


      Receive practical, actionable training and tools, including specialized templates and instruction for military and federal construction projects.

      Have any questions? 

      We'd love to hear from you.

      Check CircleFont Awesome Free 5.0.6 by @fontawesome - http://fontawesome.com License - http://fontawesome.com/license (Icons: CC BY 4.0, Fonts: SIL OFL 1.1, Code: MIT License)
      Check CircleFont Awesome Free 5.0.6 by @fontawesome - http://fontawesome.com License - http://fontawesome.com/license (Icons: CC BY 4.0, Fonts: SIL OFL 1.1, Code: MIT License)
      Check CircleFont Awesome Free 5.0.6 by @fontawesome - http://fontawesome.com License - http://fontawesome.com/license (Icons: CC BY 4.0, Fonts: SIL OFL 1.1, Code: MIT License)

      Blog + Free Resources​


      Get started for free with our collection of resources and in-depth articles on scheduling to enhance your success.

      Consulting


      Feel confident in your project schedule by ensuring it’s reliable, contractually compliant, and utilized as a tool to minimize risk.

      Whenever you’re ready, there are 3 ways we can help:

      This blog is for general informational purposes only and is not to be considered an official interpretation or enforcement policy of the UFGS standard specifications. As individual project requirements vary, refer to your specific contract. See our Terms and Conditions and Disclaimer for additional information.

      Starting with a new software can be quite intimidating, and Primavera P6 is no exception, especially if you're a newcomer. Traditional training methods can involve lengthy sessions, travel, and...
      How to Learn Primavera P6 Quickly

      How to Learn Primavera P6 Quickly: A Beginner's Guide

      Successful alignment of the project schedule and quality control system ensures a smooth start of the first phase of the 3 Phase Quality Control system. Also, it enables accurate monitoring of...
      USACE Schedule and Quality Control

      USACE Series Part 2: 

      Schedule and Quality Control

      USACE Cost Loaded Project Schedule

      USACE Series Part 1: 

      Schedule and Progress Payments

      The Schedule of Values and Construction Schedule are combined into a single Cost-Loaded Project Schedule, used to determine progress payments and provide placement projections...
      RECENT ARTICLES

      Free Checklist

      CHECKLIST - USACE SCHEDULE COST LOADING

      As the government or contractor, quickly and easily confirm your USACE schedule’s cost loading compliance with the 01 32 01.00 10 scheduling specifications.

      USACE Schedule Cost Loading Checklist

      Learn more about schedule cost loading here and CLIN balancing here

        Small Business CPM Schedule

        Navigation

        Legal

        EnvelopeFont Awesome Free 5.0.6 by @fontawesome - http://fontawesome.com License - http://fontawesome.com/license (Icons: CC BY 4.0, Fonts: SIL OFL 1.1, Code: MIT License)

        Offices located in West Granby, CT, and Forest Hill, MD

        CPM Schedule Solutions LLC provides schedule consulting and training with a focus on military construction.


        CPM Schedule Solutions LLC

        Copyright 2024 CPM Schedule Solutions LLC. All Rights Reserved.

        Contact Us

        To learn more about the schedule linking to the USACE RMS Submittal Register, see our article here.

          Free Cheat Sheet

          CHEAT SHEET - SCHEDULE LINKING TO USACE RMS SUBMITTAL REGISTER

          Learn the 5 steps to link the schedule to the submittal register in RMS for USACE projects to improve visibility and minimize the risk of delays due to late or overlooked submittals.

          USACE Schedule Submittal Register