Free Training: Construction Schedule Risk Mitigation Strategies
Published June 2021, Updated April 2023
Published May 2021, Updated February 2024
In this article, we’re discussing schedule narratives for U.S. Army Corps of Engineers (USACE) projects and breaking down the requirements.
The construction contractor’s schedule narrative communicates the context behind the schedule’s data. The narrative informs project stakeholders so everyone has the same understanding of project challenges and potential workarounds.
Schedule narratives fail to communicate this context when they are too general, withhold information that should be included, or don’t translate the data-heavy schedule information into a narrative form that can be easily understood and digested.
The objective of the schedule narrative is to communicate to the government the contractor’s thorough analysis of schedule output.
In the sections below, we discuss the specific narrative requirements with snapshots from the standard UFGS 01 32 01.00 10 scheduling specification:
For more on this topic, see our article Construction Schedule Narratives: Our Best Tips.
Check out our Schedule Narrative Template Bundle, which includes 3 professionally designed and formatted schedule narrative template files. All fully editable as word documents.
The first narrative requirement is to identify and discuss the work scheduled to start in the next update period.
Schedule activities show up as out-of-sequence when they took place out of order and the logic wasn’t updated.
Another way to think about out-of-sequence conditions for the purposes of the narrative – what was the plan before, what is it now, and why did it change?
The specifications require out-of-sequence conditions to be corrected. If the contractor wishes them to remain, they need to provide justification for the government’s approval. Out-of-sequence conditions are permitted only on a case-by-case basis.
Out-of-sequence conditions need to be identified and discussed in the narrative as well.
These changes need to be identified by activity ID and name.
How the contractor shows this information depends on what type of change comparison or forensic schedule software they use. If the software provides an excel spreadsheet, changes could be grouped and sorted with explanations added, especially if there are multiple changes for the same reason.
The narrative needs to identify and discuss any changes made in the schedule update, including:
If an activity didn’t meet it’s late start or late finish date, it will show negative float. Those activities can be targeted in the schedule for the purposes of this narrative section.
This section requires any activities that didn’t take place per their late dates be identified and discussed.
All current and anticipated issues should be identified and discussed in this section of the narrative, regardless of who caused it.
In this article, we discussed the schedule narrative requirements for U.S. Army Corps of Engineers (USACE) projects. The objective of the schedule narrative is to communicate to the government the contractor’s thorough analysis of schedule output.
The schedule narrative informs project stakeholders, so everyone has the same understanding of project challenges and potential workarounds. Schedule narratives fail when they are too general, withhold information, or don’t translate the schedule data into a narrative form that can be easily understood and digested.
Narrative requirements from the UFGS 01 32 01.00 10 specification include:
Questions or comments? Reach us at connect@cpm-ss.com.
Thanks for reading.
Related Articles:
Construction Schedule Narratives: Our Best Tips
New to USACE Schedules? 3 Things to Know
Why Quality Construction Schedules Matter
This can be discussed through grouping areas of the project work – for example, describing upcoming exterior work, interior work, and site work.
Remember – this isn’t a listing of activities sorted by the schedule’s early start date. The narrative should be kept to a narrative or discussion form, and not a data dump.
The narrative needs to identify and explain any current or anticipated problems. This includes an explanation of their impact (which schedule activities or features of work they affect), and any corrective actions that need to or have already taken place.
When the project starts the Periodic Schedule Updates, the narrative also needs to be submitted along with each draft update.
The contractor provides the draft schedule to the government, then holds the Periodic Schedule Update Meeting, and afterwards formally submits the schedule.
The narrative requires a description of the top two critical paths.
The narrative is required with each schedule submission provided to the government.
This includes:
In our Why Quality Construction Schedules Matter article, we talked about how looking at more than just the primary critical path can help you prioritize actions, so your team knows where to focus their efforts for the greatest positive return.
To make sure your schedule is calculating multiple float paths, click on the “Schedule” button (or F9 key). Click the “Options” button, then the “Advanced” tab. Make sure “Calculate multiple float paths” is selected.
Receive practical, actionable training and tools, including specialized templates and instruction for military and federal construction projects.
Have any questions?
We'd love to hear from you.
Get started for free with our collection of resources and in-depth articles on scheduling to enhance your success.
Feel confident in your project schedule by ensuring it’s reliable, contractually compliant, and utilized as a tool to minimize risk.
Whenever you’re ready, there are 3 ways we can help:
This blog is for general informational purposes only and is not to be considered an official interpretation or enforcement policy of the UFGS standard specifications. As individual project requirements vary, refer to your specific contract. See our Terms and Conditions and Disclaimer for additional information.
Starting with a new software can be quite intimidating, and Primavera P6 is no exception, especially if you're a newcomer. Traditional training methods can involve lengthy sessions, travel, and...
How to Learn Primavera P6 Quickly: A Beginner's Guide
Successful alignment of the project schedule and quality control system ensures a smooth start of the first phase of the 3 Phase Quality Control system. Also, it enables accurate monitoring of...
USACE Series Part 2:
Schedule and Quality Control
USACE Series Part 1:
Schedule and Progress Payments
The Schedule of Values and Construction Schedule are combined into a single Cost-Loaded Project Schedule, used to determine progress payments and provide placement projections...
Free Checklist
As the government or contractor, quickly and easily confirm your USACE schedule’s cost loading compliance with the 01 32 01.00 10 scheduling specifications.
Navigation
Legal
Offices located in West Granby, CT, and Forest Hill, MD
CPM Schedule Solutions LLC provides schedule consulting and training with a focus on military construction.
Copyright 2024 CPM Schedule Solutions LLC. All Rights Reserved.
Contact Us
Free Cheat Sheet
Learn the 5 steps to link the schedule to the submittal register in RMS for USACE projects to improve visibility and minimize the risk of delays due to late or overlooked submittals.